Buziv School Reconstruction

Reconstruction of the Buziv Secondary School of I - III Grades

Bucha district, Kyiv region

It was destroyed

by russian tanks 

on 6th of March 2022

At the moment, an examination of the school building has already been carried out, an assessment of the degree of destruction has been carried out, a phased reconstruction plan has been developed, an estimate documentation for the upcoming works to restore the school has been developed.
We started main building reconstruction works.

It is need 35.300.700 UAH

to rebuild school and provide all necessary equipment that children can continue their education
* Building reconstruction * Overhaul of external and internal walls * Roof repair * Windows replacement *Replacement of internal communications: electrical network, water supply, sewerage, heating network, internet *Alarm notification system *Interior decoration *Supply of furniture and necessary equipment

(source: 2022 developed reconstruction and estimate documentation)

Buziv school classroom

510 pupils

64 teachers

We have started

Work Progress

RECOVERY WORKS

AUGUST:

Dismantling of damaged structures and systems:
  • Dismantling damaged reinforced concrete structures (walls, ceilings between floors)
  • Dismantling of internal electrical networks
  • Dismantling of internal water supply and sewage networks
  • Dismantling the heating system

 

General construction works:
  • Arrangement of reinforced concrete monolithic structures (walls, overlap between floors)

 

SUPPLY OF BUILDING MATERIALS

The following building materials have already been delivered to the construction site:
  • Red brick
  • White brick
  • Construction timber
  • Metal fittings
  • Sand
  • Cement
WE CONTINUE WORKS

SEPTEMBER:

Roofing works:
  • Demolition of damaged roof 
  • Restoration of the roof structure 
  • Warming 
  • Preparation for laying tiles 
  • Tiling
     
Construction works:
  • Preparation for the reconstruction of the gym 

SUPPLY OF BUILDING MATERIALS

The following building materials have been delivered to the construction site:
  • Shingles
RESTORATION WORK CONTINUES

OCTOBER - NOVEMBER:

At the moment:
  • External work has been completed to eliminate holes from shells in the walls
  •  The roof of the main building has been completely blocked and a new roof has been made on the extension (red tiles)
  • Load-bearing structures have been strengthened,
  • All windows and entrance door structures have been replaced
Now work is:
  • Underway to install the heating system (batteries)
We collect money to continue this project

Make your impact ! Support this project ! Join us !

It was destroyed

by russian tanks 

on 6th of March 2022

At the moment, an examination of the school building has already been carried out, an assessment of the degree of destruction has been carried out, a phased reconstruction plan has been developed, an estimate documentation for the upcoming works to restore the school has been developed.
We started main building reconstruction works.

It is need 35.300.700 UAH

to rebuild school and provide all necessary equipment that children can continue their education
* Building reconstruction * Overhaul of external and internal walls * Roof repair * Windows replacement *Replacement of internal communications: electrical network, water supply, sewerage, heating network, internet *Alarm notification system *Interior decoration *Supply of furniture and necessary equipment

(source: 2022 developed reconstruction and estimate documentation)

Buziv school classroom

510 pupils

64 teachers

We have started

Work Progress

RECOVERY WORKS

AUGUST:

Dismantling of damaged structures and systems:
  • Dismantling damaged reinforced concrete structures (walls, ceilings between floors)
  • Dismantling of internal electrical networks
  • Dismantling of internal water supply and sewage networks
  • Dismantling the heating system

 

General construction works:
  • Arrangement of reinforced concrete monolithic structures (walls, overlap between floors)

 

SUPPLY OF BUILDING MATERIALS

The following building materials have already been delivered to the construction site:
  • Red brick
  • White brick
  • Construction timber
  • Metal fittings
  • Sand
  • Cement
WE CONTINUE WORKS

SEPTEMBER:

Roofing works:
  • Demolition of damaged roof 
  • Restoration of the roof structure 
  • Warming 
  • Preparation for laying tiles 
  • Tiling
     
Construction works:
  • Preparation for the reconstruction of the gym 

SUPPLY OF BUILDING MATERIALS

The following building materials have been delivered to the construction site:
  • Shingles
RESTORATION WORK CONTINUES

OCTOBER - NOVEMBER:

At the moment:
  • External work has been completed to eliminate holes from shells in the walls
  •  The roof of the main building has been completely blocked and a new roof has been made on the extension (red tiles)
  • Load-bearing structures have been strengthened,
  • All windows and entrance door structures have been replaced
Now work is:
  • Underway to install the heating system (batteries)
We collect money to continue this project

Make your impact ! Support this project ! Join us !

It was destroyed

by russian tanks 

on 6th of March 2022

At the moment, an examination of the school building has already been carried out, an assessment of the degree of destruction has been carried out, a phased reconstruction plan has been developed, an estimate documentation for the upcoming works to restore the school has been developed.

It is need 35.300.700 UAH

to rebuild school and provide all necessary equipment that children can continue their education
* Building reconstruction * Overhaul of external and internal walls * Roof repair * Windows replacement *Replacement of internal communications: electrical network, water supply, sewerage, heating network, internet *Alarm notification system *Interior decoration *Supply of furniture and necessary equipment

(source: 2022 developed reconstruction and estimate documentation)

Buziv school classroom

510 pupils

64 teachers

We have started

Work Progress

RECOVERY WORKS

AUGUST:

Dismantling of damaged structures and systems:
  • Dismantling damaged reinforced concrete structures (walls, ceilings between floors)
  • Dismantling of internal electrical networks
  • Dismantling of internal water supply and sewage networks
  • Dismantling the heating system

 

General construction works:
  • Arrangement of reinforced concrete monolithic structures (walls, overlap between floors)

 

SUPPLY OF BUILDING MATERIALS

The following building materials have already been delivered to the construction site:
  • Red brick
  • White brick
  • Construction timber
  • Metal fittings
  • Sand
  • Cement
WE CONTINUE WORKS

SEPTEMBER:

Roofing works:
  • Demolition of damaged roof 
  • Restoration of the roof structure 
  • Warming 
  • Preparation for laying tiles 
  • Tiling
     
Construction works:
  • Preparation for the reconstruction of the gym 

SUPPLY OF BUILDING MATERIALS

The following building materials have been delivered to the construction site:
  • Shingles
RESTORATION WORK CONTINUES

OCTOBER - NOVEMBER:

At the moment:
  • External work has been completed to eliminate holes from shells in the walls
  •  The roof of the main building has been completely blocked and a new roof has been made on the extension (red tiles)
  • Load-bearing structures have been strengthened,
  • All windows and entrance door structures have been replaced
Now work is:
  • Underway to install the heating system (batteries)
We collect money to continue this project

Make your impact ! Support this project ! Join us !

Donate Monobank


🎯  Goal: 1 000 000.00 ₴

🔗  https://send.monobank.ua/jar/3PzduduoGs

💳  Bank Card 
        5375 4112 0463 6299

Emergency and Reconstruction NGOs` Association